Timeline

June 2025

RFP Response

October 6, 2025

Public Meeting

October 2025

Award Recommendation Approved by ADC

Ongoing

Seek Additional Funding

Up to One Year

Remove Site for Flood Plain

January 2026

Apply for Financing

April 2026

Awards Issued, Entitlements Start

December 2026

Construction Documents and Building Permit Complete

January 2027

Start Construction

Summer 2028

Move In